Total Marine Services specialise in the design and build of marinas and floating structures. With its association with Total Floating Solutions the two companies can offer a complete turn key solution for individuals looking to berth private boats or developers looking to create a multiple berth marina.
Total Marine Services has the proven expertise and knowledge and has seen them being awarded contracts to install floating marine structures in Spain, Hong Kong and New Zealand. The diverse locations of the projects have provided Total Marine Services with the experience of working with different types of construction materials which were adapted to suit the marine environment and surrounding working conditions.
Whangamata Marina
Location : Coromandel | Date: September 2008 - September 2010
Construction of the Whangamata Marina commenced in September 2008 and was completed within 12 months. The Marina was predominately designed to cater for recreational vessels and is New Zealand’s newest marina on the Coromandel Peninsula.
Read Project DetailsOrakei Marina
Location : Auckland | Date: March 2006 - November 2008
Orakei Marina is Auckland newest marina and was opened in 2006. There are 180 berths within the marina ranging between 12m and 40m in length and the marina is protected by a solid rock breakwater on three sides. Total Marine Services were awarded the contract to install the floating pontoons, piles and miscellaneous fittings for the marina.
Read Project DetailsMotueka Marina
Location : Motueka, South Island | Date: 2008
The Motueka Marina was New Zealand’s first marina to be fully constructed in a modular plastic pontoon system. Total Marine Services and Total Floating Systems, who are the agents for Superior Jetties in New Zealand, were commissioned by the Motueka Boat Club to provide a turn key solution.
Westhaven X Pier
Location : Westhaven Marina ,Auckland | Date: Apr 2008 - Aug 2008
Westhaven Marina required the steel pipe pontoon dinghy rack and wave break alongside Pier X replaced. Total Marine Services were awarded the contract to design and re-build the 200m pier. This is a similar scenario to that of the Pier A and T renewal project.
Tutukaka Marina
Location : Tutukaka | Date: March 2011 - September 2011
The original piers (A-E) at the Tutukaka Marina were installed in 1982 and were showing signs of fatigue and failure. In December 2010, Total Marine Services were awarded the contract to rebuild the five piers at the Tutukaka Marina. The Tutukaka Marina Management Trust decided to install Total Floating Systems one piece round ended pontoons that were successfully installed at the Whangamata Marina.